CINTA DOBLE CARA +TÉCNICAS DE INSTALACIÓN DE SOLDADURA
Do not install any Aceflex sports flooring unless you are certain that the site conditions are qualified with our ground or subfloor’s requirement.
If you have any doubts about the site conditions,please contact directly with Aceflor or Aceflor authorized distributors before starting installation.
1.Requirement of subfloors
The following subfloors can be used for semi looselay installation:
·Assembled screeds
·Screeds or slabs on insulation
·Concrete floors on upper levels
These subfloors must be free from any risk of humidity at the time of installation and life long. This type of installation is recommended for use on upper levels,heated floors,old compact sports flooring,still glued corrrectly.For all other subfloors,please contact us.
·Please clarify the subfloor making sure the removal of any adhesive,paint,plaster etc..
·Tolerance of level difference is within 3mm which measured by a 2 metter rule
·All ground should be no cracks.IF there is cracks or not level,then must fill and level up well.

2.Checking the Materials
Differences of width(tolerances) may exist between the rolls.
It is advisable to check the material for defects before installation.If there are visible defects, you should inform Aceflor before using the material.
When unloading the materials from containers or trucks, take care of packing,especially the surface of flooring.Please roll or move the rolls in the direction that we roll the flooring,not in reverse direction.
Please make sure all rolls stand up in the installation facilities if the venue or subfloors are not ready for the installation.
3.Preparation of Materials
·Venue temperature and all installation should be done under minimum 15 centigrade,maximum 30 centigrade.
·Unroll and lay flatt the rolls for 24 hours along the length of the sports hall or in accordance with a floor plan before installation,let the flooring assimilate the temperature and humidity in the venue. and keeping them in order as the label pasted on the rolls,and leave a gap(1cm) between each rolls.(caution:the lengths should be unrolled starting in the center of the sports hall)
·using a flooring roller will make the material easier to install.
4 Adhering under the edges,at the periphery and infront of access areas or storage areas and on the halfway of the lengths of the rolls
·Retenga dos bordes de los rollos hasta la mitad (vea las fotos a continuación)

·Pegue un lado de la cinta de doble cara en el suelo (1) y regrese dos bordes de los rollos a su posición original sin espacios (2). Retire la tira del otro lado de la cinta (3) y luego pegue las juntas firmemente al suelo (4).


Asegúrese de que el piso se pegue firmemente al suelo.
·Repeat the process on the following rolls
·Manual roller to make sure all joints are tightly stuck down the ground and there is no bubble or air between the ground and floor whilst applying the lengths.
Note:If it is being put down on a varnished wood strip flooring,check the adhesion proporties before installating.If the subfloor shows advertising logos or stuck-down game lines,they may be damaged. So should be used Acelfor flooring protection papers before sticking double sided tape.
Precauciones:
Prohibir el tránsito o la práctica de deportes durante las 48 horas posteriores a la colocación, así como cualquier movimiento de muebles.
5. Hot welding(12hours after sticking down)
5.1 Grooving: Primero se debe probar el ranurado y la soldadura en una pequeña pieza del piso. Asegúrese de que la profundidad de la ranura sea al menos 1/3 del piso, Asegúrese de que se puedan colocar 2/3 del diámetro de la varilla de soldadura en la ranura o que sea necesario que la ranura sea más profunda.ranurar el mismo ancho en ambos bordes de dos rollos (normalmente la máquina está bien configurada para el ranurado)

Coloque el rodillo ranurador en la junta.

Asegúrese de que se puedan colocar 2/3 del diámetro de la varilla de soldadura en la ranura o que sea necesario que la ranura sea más profunda.
5.2Welding:Set the temperature mark to 2 firstly for 1 minute then to mark 3 for 1 minute,unitl reach to mark 9.Make sure the temperature is set to 9 marcado, casi alcance 850-900 grados centígrados. Luego, tire de la pistola de soldar para soldar la varilla con el piso.

5.3Trimming welding rod: Con el cuchillo de hoja lunar, corte el borde de la varilla de soldadura para asegurarse de que la superficie del piso quede lisa. Esto debe hacerse cuando la varilla esté fría.

El recorte debe realizarse en una sola pasada.
Cleaning work:
Usando un trapeador húmedo para limpiar el piso, confirme que no quede agua en la superficie.
Other accessories recommend:
Double sided tape: Aceflor double sided tape 10cm with fiber mesh inside
Paint for drawing court line:
It is screen printing ink. Some brands will tell you for pvc flooring court line drawing.
The thinner: main content is Olefin acid,not the nitro.
You will easily to find them in hardware shop or building materials market.
Welding gun: recommended leister 105407